  "energy": [
    {
      "contract_capacity_mw": 1383,
      "assumed_load_factor": 0.6,
      "annual_twh": 7.269048,
      "label": "illustrative arithmetic, not demand forecast"
    },
    {
      "contract_capacity_mw": 1383,
      "assumed_load_factor": 0.8,
      "annual_twh": 9.692064,
      "label": "illustrative arithmetic, not demand forecast"
    },
    {
      "contract_capacity_mw": 1383,
      "assumed_load_factor": 0.9,
      "annual_twh": 10.903572,
      "label": "illustrative arithmetic, not demand forecast"
    },
    {
      "contract_capacity_mw": 1383,
      "assumed_load_factor": 1.0,
      "annual_twh": 12.11508,
      "label": "illustrative arithmetic, not demand forecast"
    }
  ],
  "rate_case": [
    {
      "stage": "Initial request",
      "million_usd": 574.1
    },
    {
      "stage": "Revised request",
      "million_usd": 562.6
    },
    {
      "stage": "Authorized increase",
      "million_usd": 242.406
    }
  ],
  "annual_hours": 8760,
  "rate_request_reduction_million": 331.694,
  "authorized_share_initial": 0.42223654415607037,
  "minimum_demand_illustration_mw": 1106.4,
  "qualification": "80% billing demand is not an energy consumption promise; ramp-period contract capacity may differ"
}